The Tahuehueto Project consists of 28 mining concessions grouped into five non-contiguous blocks that total approximately 7,492 hectares. Tahuehueto lies within the prolific Sierra Madre Mineral Belt, which hosts a series of historic and producing mines and most of Mexico's active exploration and development projects. The project is situated about 25 km north of the Topia polymetallic-silver mine, 65 km northwest of the La Cienega gold, silver, base metal mine, 85 km southwest of the Guanacevi silver district, 280 km southeast of the Palmarejo silver and gold mine and 150 km northwest of the San Dimas mining district, most notable for the Tayoltita silver and gold mine.
On January 23, 2017 Telson announced the results of a Pre-Feasibility Study ("PFS") completed by Metal Mining Consultants Inc. Key findings from the report included:
| SUMMARY OF ECONOMIC RESULTS FROM 2016 PRE-FEASIBILITY STUDY | |
| Item | |
| Average Annual Revenues ("EBITDA") | US $16.7 million |
| NPV @ 8% Annual Discount Rate (Post Tax) | US $77 million |
| Internal Rate of Return (IRR) | 36% |
| Payback Period | 3 years |
| Mine Life | 21 years |
| Average Cost per Tonne (incl mining, processing and G&A) | US $59.24 |
| Average Cost per Ounce AuEq | US $305.00 |
| METAL PRICES | |
| Gold | US$ 1,180.00/oz |
| Silver | US$ 16.70/oz |
| Lead | US$ 0.87/lb |
| Zinc | US$ 0.92/lb |
| Copper | US$ 2.65/lb |
ACCESS
Access to the Tahuehueto property is by paved Mexican Highway 45 from the city of Durango, 53 km to the turnoff to Santiago Papasquiaro, then west on paved Mexican Highway 23 for 122 km through Santiago Papasquiaro and on to Tepehuanes. From Tepehuanes, an unnumbered paved road runs west through El Tarahumar. The pavement ends approximately 65 km after Tepehuanes, and access is then by 120 km of dirt road to the project. There is also access via fixed wing aircraft from either Culiacan or Durango with a gravel airstrip located 20 km by road north or Tahuehueto.
OWNERSHIP
Telson Resources Inc. controls 100% of the Tahuehueto Project through its 99% owned Mexican subsidiary.
MINERALIZATION
Since acquiring the rights to the Tahuehueto Project in 1997, Telson Resources has identified at least 12 polymetallic zones hosted within a structurally controlled epithermal system that has been traced for more than six kilometres. Mineralization at Tahuehueto consists of epithermal, low-sulfidation, polymetallic Ag-Au veins and breccias with copper, lead and zinc. This setting is common within the gold-silver metallogenic province of the Sierra Madre Occidental and accounts for much of the historic gold and silver production from the province.
METALLURGICAL TESTING
Concentrate recoveries in its most recent Pre-Feasibility Study released on January 23, 2017 are shown in the table below.
| Product |
kTonnes |
Distribution % (Recoveries) | ||||
| Au | Ag | Cu | Pb | Zn | ||
| Head | 3,264 | 100% | 100% | 100% | 100% | 100% |
| Pb Concentrate | 58 | 77.1% | 62.8% | 31.6% | 85.5% | 1.6% |
| Cu Concentrate | 18 | 6.8% | 10.3% | 51.4% | 0.6% | 17.1% |
| Zn Concentrate | 108 | 11.0% | 11.7% | 11.5% | 6.1% | 80.0% |
| Tails | 3,096 | 5.4% | 15.2% | 5.4% | 7.8% | 1.3% |
SUMMARY
Mr. Ralph Shearing, President of the Company states "With the delivery of this Pre-Feasibility Study we are now able to present to shareholders a clear path forward to achieve the Company's goal of commercial production at Tahuehueto. Management is committed to this goal and will continue with its numerous initiatives already in progress to secure the necessary mine build funding, as well as to progress development and engineering work currently underway on site, advancing the project towards production throughout the coming year".